The Town of Scott, Monroe County, Wi. bid opening for the town ARIP was held on Thursday, May 7, 2026 at 10AM at the Town of Scott Hall, 28788 Buckley Ave. The following were the bid proposals presented:
Road Reconstruction on 2 miles section of Copper Road:
Gerke Excavating $710,531.37
Lepke Trucking Excavation $656,777.77
Stout Construction $699,966.45
Pavement Improvement 2 miles 3.5” HMA
Mathy Construction $596,080.61
Scott Construction $687,612.00
Copper Road ARIP (alternate) pavement 17,600 square feet Brunswick Ave
Mathy Construction $40,522.89
Scott Construction $37,560.00
Bids will be awarded at the May 14, 2026 May Town Board Meeting.
Jim Van Wychen, Clerk, Town of Scott, Monroe County
Town of Scott, Monroe County, Wi. ARIP (Agricultural Road Improvement Project) Bid Opening.